AQL
Acceptable Quality LimitThe highest share of defective units a buyer will accept in a sampled inspection, set under ISO 2859-1. Apparel buyers commonly inspect at AQL 2.5 for major defects and 4.0 for minor ones: an inspector pulls a sample sized to the lot, and the lot passes or fails on how many defects the sample contains.
In FactoryPlus Quality checks are part of the base: QC results are recorded against each order before it is marked for delivery.
BOM
Bill of materialsThe list of every material that goes into one garment: fabric, lining, thread, buttons, zips, labels, tags and packing, each with its consumption per piece. Multiplied by the order quantity and a wastage allowance, the BOM tells purchasing what to buy.
In FactoryPlus Styles and BOMs are part of the base. Issuing material to production deducts it from stock, and reorder warnings arrive before cutting stops.
CMP
Cut, make, packA manufacturing model where the buyer supplies fabric and trims, and the factory cuts, sews and packs the garments for a processing fee. Like CMT, but the factory also handles final packing.
CMT
Cut, make, trimA manufacturing model where the buyer supplies the fabric and usually the trims, and the factory charges only for cutting, sewing and finishing. Margins are thinner than FOB, but the factory carries no material risk.
Costing sheet
The breakdown that turns a style into a price: fabric and trims from the BOM, labour from the SMV and cost per minute, overheads, washing or printing, packing, freight and margin. A wrong costing sheet loses money on every piece shipped.
In FactoryPlus Costing and margin are part of the base, with margin per piece visible for every order.
Cut-to-ship ratio
Pieces shipped divided by pieces cut. It shows how much is lost between the cutting table and the carton to rejects, damage and miscounts. Well-run factories track it per order, because a few percent lost on every order adds up.
DHU
Defects per hundred unitsThe number of defects found per 100 garments checked: total defects ÷ units inspected × 100. One garment can carry several defects, so DHU can be higher than the percentage of defective pieces. Tracked per line and per operation, it shows where quality is slipping.
FOB
Free on boardIn apparel, a full-package model: the factory sources the materials, makes the garments and delivers them loaded at the port of origin. The FOB price covers materials, making, overheads and margin, and the factory carries the material risk.
Line balancing
Spreading a garment's operations across the operators on a sewing line so each station takes about the same time. An unbalanced line piles up work in front of the slowest operation and starves the ones after it.
Line efficiency
Output measured against the time available: (pieces produced × SMV) ÷ (operators × minutes worked) × 100. A line of 30 operators working 480 minutes that produces 900 pieces of a 10-minute garment runs at 62.5% efficiency.
Marker efficiency
The share of a cutting marker's fabric area covered by pattern pieces. Since fabric is usually the largest cost in a garment, a few points of marker efficiency make a visible difference to margin.
OTIF
On time, in fullThe share of orders delivered by the agreed date and in the full quantity. Buyers score suppliers on it, and late or short shipments can lead to penalties, air freight at the factory's cost or lost repeat orders.
In FactoryPlus Head office sees every order's stage-by-stage progress live, so a line falling behind shows up before the ship date, not after.
PP sample
Pre-production sampleA garment made with the actual bulk fabric and trims and approved by the buyer before bulk production starts. It's the last chance to catch fit, colour or construction problems cheaply.
SMV
Standard minute value, also SAMThe time a trained operator, working at a standard pace, needs to complete an operation or a whole garment, including allowances for fatigue and delays. Factories use SMV to price labour, set line targets and work out how many pieces a line can make in a day.
Tech pack
The buyer's technical specification for a style: sketches, measurements and grading, materials, construction details, labels, artwork and packing instructions. The factory builds its BOM and costing from it.
TNA
Time and action calendarThe schedule of every milestone in an order, from fabric booking and sample approval to cutting, sewing, inspection and shipment, worked backwards from the ship date. A missed early milestone is the first warning of a late shipment.
WIP
Work in progressGarments that have been cut but not yet finished, sitting between operations. Some WIP keeps a line moving; too much hides bottlenecks, ties up money and makes it hard to say where an order actually is.
In FactoryPlus Each production order moves through your own stages, and the floor records daily good and defect counts per stage, so WIP is visible by order and by stage.
FactoryPlus pilot
Run a garment factory? Let's shape yours.
Tell us how many factories you run and how you track production today. We'll show you FactoryPlus on your own styles.